| Question 
 [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
 | 
 What is not correct about ABC: 
|  |  Less accurate 
 | 
|  |  Difficult to implement 
 | 
|  |  Time consuming 
 | 
|  |  Massive amount of data 
 | 
 Explanation: 
Detailed explanation-1: -Answer and Explanation: The answer is (c) It requires few calculations to determine the costs of products and services.
Detailed explanation-2: -Fewer cost pools used to assign overhead costs to products is not a benefit of activity based costing.
Detailed explanation-3: -Activity based costing systems are more accurate than traditional costing systems. This is because they provide a more precise breakdown of indirect costs. However, ABC systems are more complex and more costly to implement.
Detailed explanation-4: -Accordingly, the preparation of allocation matrices is not normally associated with ABC costing. It is usually used in the based-cost allocation method.