Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
At the 0 (zero) direct labor-hour level on the flexible-budget graph, total budgeted costs intersect the vertical axis at $30,000. At the 10,000 direct labor-hour level on the horizontal axis, total budgeted costs intersect the vertical axis at
A
$30,000 fixed costs + $6 per direct labor hour as variable costs.
B
$30,000 fixed costs + $9 per direct labor hour as variable costs.
C
$60,000 fixed costs + $3 per direct labor hour as variable costs.
D
$60,000 fixed costs + $6 per direct labor hour as variable costs.
Explanation: 