ECONOMICS

COST ACCOUNTING

CAPITAL BUDGETING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is NOT a factor that a manager should bear in mind when estimating a project’s revenues and costs?
A
Sales of a product will typically accelerate, stabilize, and then decline as the product becomes outdated or faces increased competition.
B
A new product typically has its highest sales immediately after release as customers are attracted by the novelty of the product.
C
The prices of technology products tend to fall over time as newer, superior technologies emerge and production costs decline.
D
Prices and costs tend to rise with the general level of inflation in the economy.
Explanation: 

Detailed explanation-1: -Answer: The correct answer is option B. Explanation: Capital budgeting considers the opportunity cost.

Detailed explanation-2: -As they involve huge costs one wrong decision would have a big effect on the business. They include all the potential expenses/costs. It includes opportunity cost, actual cost, incremental and relevant cash flows. It does not include sunk costs.

Detailed explanation-3: -Which of the following is most likely an assumption of capital budgeting? Any taxes involved need to be ignored. Decisions are based on net income.

Detailed explanation-4: -The answer is: d. to determine the effect of the decision to accept or reject a project on the firm’s cash flows. Capital budgeting is a process used by firms to determine whether or not to accept or reject a project. This decision is made based on the project’s anticipated future cash flows.

There is 1 question to complete.