COST ACCOUNTING
CAPITAL BUDGETING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
It does not allow for projects to be ranked.
|
|
It has an inadequate reinvestment assumption.
|
|
It is likely that there will be more than one NPV for a project.
|
|
All of the above
|
Detailed explanation-1: -Answer and Explanation: The false statement is A) Reject projects with a NPV of zero, as accepting them is equivalent to reducing firm value. The NPV is a method to calculate the current value of all future cash flows of a project to evaluate its profitability.
Detailed explanation-2: -Answer and Explanation: The correct answer is A) Accept a project if NPV > cost of investment. The net present value estimates the current worth of a project by taking the present value of the future cash flows minus the cost of investment.
Detailed explanation-3: -The discount rate may reflect your cost of capital or the returns available on alternative investments of comparable risk. If the NPV of a project or investment is positive, it means its rate of return will be above the discount rate.
Detailed explanation-4: -The IRR must be greater than 0 is true if the Net Present Value (NPV) of a positive.