COST ACCOUNTING
STANDARD COSTING AND VARIANCE ANALYSIS
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
A product has standard material cost of $32 (4 kg × $8). During May, 3, 000 kg were purchased at a cost of $23, 000. The material usage variance for May was $1, 600 adverse and the material price variance was $1, 000 favourable. The company hold no inventory. What was the actual production level for May?
|
700 units
|
|
750 units
|
|
800 units
|
|
850 units
|
Explanation:
Detailed explanation-1: -14 (Adverse) (b) Calculation of Material usage Variance : Material usage variance = Standard quantity of material-Actual quantity of material x Standard price per unit.
Detailed explanation-2: -The materials cost variance formula is Price Variance + Quantity Variance. Price Variance is found with the formula (AQ * AP)-(AQ * SP). Quantity Variance is found with the formula (AQ * SP)-(SQ * SP).
Detailed explanation-3: -Below are some of the Variance Analysis formulae that one can apply: Material Cost Variance Formula = Standard Cost – Actual Cost = (SQ * SP) – (AQ * AP) Labor Variance Formula= Standard Wages – Actual Wages = (SH * SP) – (AH * AP)
There is 1 question to complete.