COST ACCOUNTING
STANDARD COSTING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
The total variance is RM35, 000. The total materials variance is RM14, 000. The total labor variance is twice the total overhead variance. What is the total overhead variance?
|
RM3, 500
|
|
RM7, 000
|
|
RM10, 500
|
|
RM14, 000
|
Explanation:
Detailed explanation-1: -It can be calculated using the following formula: Fixed Overhead Volume Variance = Applied Fixed Overheads – Budgeted Fixed Overhead. Here, Applied Fixed Overheads = Standard Fixed Overheads × Actual Production.
Detailed explanation-2: -It is calculated as (budgeted production hours minus actual production hours) x (fixed overhead absorption rate divided by time unit), Fixed overhead efficiency variance is the difference between absorbed fixed production overheads attributable to the change in the manufacturing efficiency during a period.
Detailed explanation-3: -The total overhead variance is the difference between actual overhead costs and overhead costs applied to work done.
There is 1 question to complete.