ECONOMICS

COST ACCOUNTING

STANDARD COSTING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The total variance is RM35, 000. The total materials variance is RM14, 000. The total labor variance is twice the total overhead variance. What is the total overhead variance?
A
RM3, 500
B
RM7, 000
C
RM10, 500
D
RM14, 000
Explanation: 

Detailed explanation-1: -It can be calculated using the following formula: Fixed Overhead Volume Variance = Applied Fixed Overheads – Budgeted Fixed Overhead. Here, Applied Fixed Overheads = Standard Fixed Overheads × Actual Production.

Detailed explanation-2: -It is calculated as (budgeted production hours minus actual production hours) x (fixed overhead absorption rate divided by time unit), Fixed overhead efficiency variance is the difference between absorbed fixed production overheads attributable to the change in the manufacturing efficiency during a period.

Detailed explanation-3: -The total overhead variance is the difference between actual overhead costs and overhead costs applied to work done.

There is 1 question to complete.