Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Who is responsible for a materials price variance?
A
The Purchasing Agent.
B
The Production Manager
C
The Production & Maintenance Managers
D
Supervisor
Explanation: 

Detailed explanation-1: -Ideal standards should be used for forecasting and planning. 4. In general, the purchasing agent is responsible for the material price variance.

There is 1 question to complete.