Which of the following helps managers track the issues that arise in a project and prioritize a response to them?
A
Issue tracker
B
Issue list
C
Track list
D
Issue builder
Explanation: 

Detailed explanation-1: -An issue log is a simple list or spreadsheet that helps managers track the issues that arise in a project and prioritize a response to them.