The LAST step in the landscape project development process is to:
A
bill the customer for work done
B
determine the need or objective
C
develop a maintenance schedule
D
select a maintenance contractor
Explanation: 

Detailed explanation-1: -The five steps of the design process include: 1) conducting a site inventory and analysis, 2) determining your needs, 3) creating functional diagrams, 4) developing conceptual design plans, and 5) drawing a final design plan.

Detailed explanation-2: -The principles of landscape design include the elements of unity, scale, balance, simplicity, variety, emphasis, and sequence as they apply to line, form, texture, and color. These elements are interconnected.