Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Project-based learning instruction is effective when ____
A
The principal fully embraces it
B
Teachers fully embraces it
C
When teachers have time to plan quality PBL units
D
All of the above
Explanation: 

Detailed explanation-1: -Project-based learning helps students develop teamwork and problem-solving skills14, along with the ability to communicate effectively with others. The collaborative nature of projects also reinforces the Social and Emotional Learning (SEL) programs being implemented at progressive schools around the world.

Detailed explanation-2: -Larmer, Mergendoller, and Boss (2015) outline four key phases of Project-Based Learning: project launch, inquiry, development (which includes critique and revision), and presentations.

Detailed explanation-3: -PBL is a flexible and engaging teaching approach that can be used to design new lessons or to improve lessons you have previously. Educators use PBL for many reasons, including increased student engagement, possibilities for teaching and assessing multiple skills, and possibilities for differentiation.