Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
____ is a horizontal bar chart with a list of activities on the left and a timeline on the horizontal axis.
A
PERT chart
B
Activity-on-diagram chart
C
Gantt chart
D
Network diagram chart
Explanation: 

Detailed explanation-1: -Definition. A Gantt chart is a type of bar chart that illustrates a project schedule. This chart lists the tasks to be performed on the vertical axis, and time intervals on the horizontal axis. The width of the horizontal bars in the graph shows the duration of each activity.

Detailed explanation-2: -A gantt chart is a horizontal bar chart used in project management to visually represent a project plan over time. Gantt charts typically show you the timeline and status-as well as who’s responsible-for each task in the project.

Detailed explanation-3: -A Gantt chart is a 2-dimensional chart of a sequence of tasks and their dependencies while a timeline is a simpler visualization of events on a single line. A Gantt chart offers you a microscopic view of every detail of your project like current task progress, task priorities, milestones, time estimates, etc.

There is 1 question to complete.