Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
A project schedule is created ____ the scope planning has created the WBS and ____ project resource planning.
A
before, after
B
when, over
C
after, before
D
in between, after
Explanation: 

Detailed explanation-1: -A work breakdown structure (WBS) is a project management tool that takes a step-by-step approach to complete large projects with several moving pieces. By breaking down the project into smaller components, a WBS can integrate scope, cost and deliverables into a single tool.

Detailed explanation-2: -A Work Breakdown Structure (WBS) identifies tasks and deliverables associated with a project. Resources are identified for each item within the WBS that facilitates budgeting as well as assignment of responsibilities. T he WBS can be used to determine the critical path of the project and create the project schedule.