Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Project closing is ____
A
processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken.
B
the processes used to complete the work defined in the project plan to accomplish the project’s requirements
C
the formal acceptance of the project and the ending thereof.
D
to plan time, cost and resources adequately to estimate the work needed and to effectively manage risk during project execution
Explanation: 

Detailed explanation-1: -In other words, Project Closing is the combination of the following when applied to a project: Assurance that all the work has been completed, Assurance that all agreed upon project management processes have been executed, and. Formal recognition of the completion of a project-everyone agrees that it is completed.

Detailed explanation-2: -Project closure is the critical last phase in the project management lifecycle. During project closure, the team reviews the deliverables, then compares and tests its quality to the intended project outcome. Then they share the deliverables with the project’s client.

Detailed explanation-3: -Closing includes the formal acceptance of the project and the ending thereof.