COMPUTER NETWORKING

MULTIMEDIA AND QUALITY OF SERVICE

INTRODUCTION

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Project initiation ____
A
consists of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be taken
B
includes planning of time, cost and resources adequately to estimate the work needed and to effectively manage risk during project execution
C
involves coordinating people and resources, as well as integrating and performing the activities of the project in accordance with the project management plan.
D
determines the nature and scope of the project
Explanation: 

Detailed explanation-1: -Defining project scope requires input from the project stakeholders. They work with project managers to establish the key elements of budget, objectives, quality and timeline. To determine scope, project managers must collect requirements for what the stakeholders need from the project.

Detailed explanation-2: -What is project initiation? Project initiation is the first step in starting a new project. During the project initiation phase, you establish why you’re doing the project and what business value it will deliver-then use that information to secure buy-in from key stakeholders.

Detailed explanation-3: -Project initiation is the first phase of the project management life cycle and in this stage, companies decide if the project is needed and how beneficial it will be for them. The two metrics that are used to judge a proposed project and determine the expectations from it are the business case and feasibility study.

There is 1 question to complete.