Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Project planning deals with the following activities EXCEPT ____
A
developing the scope statement
B
identifying deliverables and creating the work breakdown structure
C
finalize all activities across all of the process groups to formally close the project or a project phase
D
estimating the resource requirements for the activities
Explanation: 

Detailed explanation-1: -“Close Project or Phase is the process of finalizing all activities for the project, phase, or contract. The key benefits of this process are the project or phase information is archived, the planned work is completed, and organizational team resources are released to pursue new endeavors.

Detailed explanation-2: -initiation. planning. execution. monitoring and control. closure.

Detailed explanation-3: -Define stakeholders. Stakeholders include anyone with an interest in the project. Define roles. Each stakeholder’s role should be clearly defined. Introduce stakeholders. Set goals. Prioritize tasks. Create a schedule. Assess risks. Communicate. More items