Which statement of WBS below is incorrect?
A
WBS is useful for complex projects
B
WBS defines the work required to achieve an objective
C
WBS provides timing of activities
D
WBS is a tool for planning & scheduling a project
Explanation: 

Detailed explanation-1: -The answer is A. The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

Detailed explanation-2: -You do not list time components or dependencies in a WBS to keep a clear focus on the work to be done. A WBS should be created before a detailled project plan as it is a basis to estimate the resources needed and to create a cost and time schedule.

Detailed explanation-3: -The first (top) level of the WBS is the project title and the final deliverable. The second WBS level is control accounts. The third WBS level is work packages. The last one of the WBS levels is activities. More items •04-May-2022