Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The proper time to develop a revised and detailed project plan for the client and finalize your budget and payment schedule for the continuation of the project is:
A
at the end of thepilot phase
B
at the end of beta development
C
before developing theprototype
D
during pretesting
Explanation: 

Detailed explanation-1: -The elements are budget/cost, time/schedule, and scope. If a change is posed to any one of these elements, something else must change.

Detailed explanation-2: -Non-linear Structure Users can navigate freely through the content, unbound by predetermined routes.

Detailed explanation-3: -A series of graphics that outline the visual details of a multimedia project is called: A storyboard.

There is 1 question to complete.