MCQ IN COMPUTER SCIENCE & ENGINEERING

COMPUTER SCIENCE AND ENGINEERING

ALGORITHMS

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The interval from the time of submission of a process to the time of completion is termed as
A
waiting time
B
turnaround time
C
response time
D
throughput
Explanation: 

Detailed explanation-1: -Turnaround time (TAT) is defined as the total time interval between the time of process submission and the time of its completion.

Detailed explanation-2: -Turnaround Time vs Response Time: Turnaround time is the amount of time elapsed from the time of submission to the time of completion whereas response time is the average time elapsed from submission until the first response is produced.

Detailed explanation-3: -Burst Time The total amount of time required by the CPU to execute the whole process is called the Burst Time.

Detailed explanation-4: -Therefore, the time required for a particular process to complete, from submission time to completion is called Turnaround time.

Detailed explanation-5: -Answer: Execution Time: The serial runtime of a program is the time elapsed between the beginning and the end of its execution on a sequential computer.

There is 1 question to complete.