After the finalization of SRS, we may like to estimate
A
Size
B
Cost
C
Development time
D
All of these
Explanation: 

Detailed explanation-1: -Which of the following is included in SRS ? Explanation: Design constraints include standards to be incorporated in the software, implementation language, resource limits, operating environment etc. 7.

Detailed explanation-2: -16. Identify the correct option among the following which is not included in SRS? Answer-D) Design solutions are not included in SRS.

Detailed explanation-3: -Software Requirements Specifications, also known as SRS, is the term used to describe an in-depth description of a software product to be developed. It’s considered one of the initial stages of the software development lifecycle (SDLC).

Detailed explanation-4: -Detailed Solution. The SRS document produced at the end of the requirement analysis phase is called the Black Box specification.

There is 1 question to complete.