COMPUTER SCIENCE AND ENGINEERING
SOFTWARE ENGINEERING
Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
True
|
|
False
|
|
Either A or B
|
|
None of the above
|
Detailed explanation-1: -Explanation: There are three phases in Scrum.The initial phase is an outline planning phase followed by a series of sprint cycles and project closure phase. 7. Agile methods seem to work best when team members have a relatively high skill level.
Detailed explanation-2: -Agile works really well when the product vision or features are not well defined. Agile allows product owners to adjust requirements and priorities along the way to take advantage of opportunities and ultimately deliver a better product to all of the project stakeholders.
Detailed explanation-3: -Scrum. Scrum is one of the main Agile methods and is arguably the most used among teams. It involves several roles including a Scrum Master (the team leader and facilitator), a Development Team, and an Initiative Owner.
Detailed explanation-4: -Answer: B) Agile methodology is an iterative approach to software development. Explanation: An agile methodology is an iterative approach to software development.
Detailed explanation-5: -The studies indicate that agile methods positively influence team effectiveness through psychological safety, transparency, communication, emphasis on face-to-face communication, and contribution to team wellbeing.