Choose the correct option according to given below statement. Statement 1:Umbrella activities are independent of any one framework activity and occur throughout the process. Statement 2:software quality assurance, software configuration management are umbrella activity. Statement 3:software quality assurance, software configuration management are not umbrella activity.
A
Only statement 1 is correct.
B
Statement 1 and statement 2 are correct.
C
Only statement 3 is correct.
D
Statement 1 and statement 3 are correct.
Explanation: 

Detailed explanation-1: -Umbrella Activities are as follows: Software Project Tracking and Control. Formal Technical Reviews. Software Quality Assurance. Software Configuration Management.

Detailed explanation-2: -Umbrella activities are the activities that span all the stages of the SDLC. umbrella activities include: software project management. formal technical reviews.

Detailed explanation-3: -Which one of the following is not an Umbrella Activity that complements the five process framework activities and help team manage and control progress, quality, change, and risk. Explanation: None.