If a timebox (iteration) plan needs to be reprioritised in a hurry, who should re-prioritise?
|
The developers alone (they know what the customer wants by now)
|
|
The customer alone (the developers would only choose the easy things as top priority)
|
|
The Project Leader (they can give an independent, pragmatic view)
|
|
The whole team including customer and developers (together they can consider both business value and practicality)
|
Explanation: