If you were a lead developer of a software company and you are asked to submit a project/product within a stipulated time-frame with no cost barriers, which model would you select?
A
Waterfall
B
Spiral
C
RAD
D
Incremental
Explanation: 

Detailed explanation-1: -Which of the following life cycle model can be chosen if the development team has less experience on similar projects? Explanation: Relying on risk assessment/analysis provides more flexibility than required for many applications which overcomes the criteria of less experienced developers.

Detailed explanation-2: -21. Which of the following models will not result in the desired output, when the user participation isn’t involved? RAD and prototyping are the models which are dependent upon the user’s participation and might produce undesired output.

Detailed explanation-3: -1 Answer. Best explanation: Real projects rarely follow the sequential flow and iterations in this model are handled indirectly. This changes can cause confusion as the project proceeds thereby delaying the delivery date.

Detailed explanation-4: -Prototyping & Waterfallc. Spiral & Prototypingd. Spiral & RADAnswer: Option (c)Transitionalb.