In CMM, the life cycle activities of requirements analysis, design, code, and test are described in
A
Software Product Engineering
B
Software Quality Assurance
C
Software Subcontract Management
D
Software Quality Management
Explanation: 

Detailed explanation-1: -Explanation: In CMM planning these activities is described in Software Project Planning, however the life cycle activities of requirements analysis, design, code, and test are described in Software Product Engineering.

Detailed explanation-2: -CMM which stands for Capability Maturity Model is a benchmark to measure the maturity of an organization’s software development process. EXPLANATION: The Capability Maturity Model is used to analyze techniques used in developing software products in any organization.

Detailed explanation-3: -5. Which of these software engineering activities are not a part of software processes ? Explanation: Software dependence is an attribute and not an engineering activity for process.

Detailed explanation-4: -3. Which one of the following is not a step of requirement engineering? Explanation: Requirement Elicitation, Requirement Analysis, Requirement Documentation and Requirement Review are the four crucial process steps of requirement engineering. Design is in itself a different phase of Software Engineering.

Detailed explanation-5: -The Capability Maturity Model (CMM) is a methodology used to develop and refine an organization’s software development process. The model describes a five-level evolutionary path of increasingly organized and systematically more mature processes.