In COCOMO model, if project size is typically 2-50 KLOC, then which mode is to be selected?
A
Organic
B
Semidetached
C
Embedded
D
Productive
Explanation: 

Detailed explanation-1: -The project schedule is not very tight. Calculate the Effort, development time, average staff size, and productivity of the project. Solution: The semidetached mode is the most appropriate mode, keeping in view the size, schedule and experience of development time.

Detailed explanation-2: -Basic COCOMO Model It requires to calculate the efforts which are required to develop in three modes of development that are organic mode, semi-detached mode, and embedded mode.

Detailed explanation-3: -KLOC = The size of the code for the project in Kilo lines of code. a, b, c, d = The constant parameters for the software project.

Detailed explanation-4: -COCOMO-II was designed and developed in University of Southern California by Barry Boehm in 1997 as a successor of the earlier Constructive Cost Model (COCOMO). It is based on the algorithm approach and is designed is to give better and enhanced support to the new software development.