Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
One indicator of the success of a software development project is deliverable work which includes: programs/applications, documents, and several other services
A
Fact
B
Myth
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -Successful projects are those that 1) meet business requirements, 2) are delivered and maintained on schedule, 3) are delivered and maintained within budget, and 4) deliver the expected business value and return on investment.

Detailed explanation-2: -Shenhar, Dvir, Levy, and Maltz (2001) demonstrated empirically that project success is composed of the four factors of efficiency (cost and schedule), customer impact (multiple measures), business success (commercial success and market share), and future preparation (multiple measures).