MCQ IN COMPUTER SCIENCE & ENGINEERING

COMPUTER SCIENCE AND ENGINEERING

SOFTWARE ENGINEERING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Software engineering umbrella activities are only applied during the initial phases of software development projects.
A
True
B
False
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -Software engineering umbrella activities are only applied during the initial phases of software development projects. The correct answer is ‘False’.

Detailed explanation-2: -The umbrella activities of a software process are: Software project tracking and control. Risk Management. Software Quality Assurance.

Detailed explanation-3: -Which one of the following is not an Umbrella Activity that complements the five process framework activities and help team manage and control progress, quality, change, and risk. Explanation: None.

Detailed explanation-4: -Answer: The umbrella activities occur throughout the software process they are applied evenly across the process, the analysis encompasses a set of work tasks (eg. requirement gathering, elaboration, negotiation specification and validation).

Detailed explanation-5: -Which of these software engineering activities are not a part of software processes ? Explanation: Software dependence is an attribute and not an engineering activity for process.

There is 1 question to complete.