Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
What is the first activity in Software Project Planning?
A
Determination of software scope
B
Determination of budget
C
Find out the team size
D
None of these
Explanation: 

Detailed explanation-1: -The first activity in software project planning is the determination of software scope. Function and performance allocated to software during system engineering should be assessed to establish a project scope that is understandable at the management and technical levels.

Detailed explanation-2: -Explanation: The first phase of the software development life cycle is the requirement analysis, in which the software engineer analyzes the software requirement based on the user’s outlook.

Detailed explanation-3: -Explanation: The first step in project planning is to establish the objectives and scope.

Detailed explanation-4: -Project initiation is the first step in starting a new project. During the project initiation phase, you establish why you’re doing the project and what business value it will deliver-then use that information to secure buy-in from key stakeholders.