What is the process of analyzing, documenting, tracking, prioritizing and agreeing on the requirement and controlling the communication to relevant stakeholders?
A
Requirement Management
B
Requirement Elicitation
C
Requirement Analysis
D
Requirement verification
Explanation: 

Detailed explanation-1: -Requirements management is the process of documenting, analyzing, tracing, prioritizing and agreeing on requirements and then controlling change and communicating to relevant stakeholders.

Detailed explanation-2: -DEFINITION OF REQUIREMENTS MANAGEMENT. Requirements Management is the process of gathering, analyzing, verifying, and validating the needs and requirements for the given product or system being developed. Successful requirements management ensures that completed deliverables meet the expectations of the stakeholders.

Detailed explanation-3: -The purpose of elicitation is to identify the needs and constraints of various project stakeholders (Wiegers 1999). The results of this process are a common understanding among the project stakeholders of the users’ expressed needs.

Detailed explanation-4: -A requirements management plan is a document that is typically created alongside the primary project plan as a piece of the scope management process. Its primary purpose is to ensure that all stakeholder and business requirements are captured, analyzed, managed, and addressed by the project plan.