Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
|
The Sprint items are no longer needed
|
|
Sprint can never be canceled
|
|
When Development is unable to complete the work
|
|
Information required to start the development is not available
|
|
Whenever the Product Owner says
|
Detailed explanation-1: -A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint. This opens it up to the Scrum Team to decide what comes next should a Sprint Goal become obsolete, and the PO decide to cancel a Sprint.
Detailed explanation-2: -Q #5) When can a Sprint be canceled? The power to cancel the Sprint lies only with the Product Owner. He/She can call to cancel an ongoing Sprint when the Sprint Items are no longer required by the business i.e. the items have become obsolete.
Detailed explanation-3: -The time, efforts and at times work done might be considered waste and Product Owner takes the accountability of any such business impacts. A Sprint can be cancelled before the Sprint duration ends.
Detailed explanation-4: -What to do with the work already “done”? “When a Sprint is cancelled, any completed and “Done” Product Backlog items are reviewed. If part of the work is potentially releasable, the Product Owner typically accepts it.”-The Scrum Guide.