Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is a project scheduling method that can be applied to software development?
A
PERT
B
CPM
C
CMM
D
Both PERT and CPM
Explanation: 

Detailed explanation-1: -9. Which of the following is a project scheduling method that can be applied to software development? Explanation: Program evaluation and review technique (PERT) and critical path method (CPM) are two project scheduling methods that can be applied to software development.

Detailed explanation-2: -PERT is used to schedule, organize, and coordinate tasks within a project. It is basically a method to analyze the tasks involved in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project.

Detailed explanation-3: -The critical path method (CPM) is a technique where you identify tasks that are necessary for project completion and determine scheduling flexibilities. A critical path in project management is the longest sequence of activities that must be finished on time in order for the entire project to be complete.

Detailed explanation-4: -Critical path method. The critical path method is perhaps the most popular of all methods for scheduling in construction management. It involves identifying the resources and time required to complete a milestone, as well as how the set goal is relevant to the overall project.