MCQ IN COMPUTER SCIENCE & ENGINEERING

COMPUTER SCIENCE AND ENGINEERING

SOFTWARE ENGINEERING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which of the following is an activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks?
A
Software Macroscopic schedule
B
Software Project scheduling
C
Software Detailed schedule
D
None of the mentioned
Explanation: 

Detailed explanation-1: -Software project scheduling-activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks.

Detailed explanation-2: -Software project scheduling is an activity that distributes estimated effort across the planned project duration, True.

Detailed explanation-3: -Explanation: a recommended distribution of effort across the software process is 40% (analysis and design), 20% (coding), and 40% (testing).

Detailed explanation-4: -Task set is a collection of software engineering work tasks, milestones and deliverables that must be accomplished to complete a particular software project.

Detailed explanation-5: -Critical Path Method (CPM) The CPM method is a commonly used construction scheduling method that helps managers predict the project schedule based on its tasks. To do this, you need to: List all of the assignments required to complete your project in a Work Breakdown Structure. Estimate the duration of each task.

There is 1 question to complete.