Question
[CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
|
Which of the following is not an effective software project management focus:
|
Process
|
|
Product
|
|
Popularity
|
|
People
|
Explanation:
Detailed explanation-1: -Explanation: Popularity is not an effective software project management focus. The four P’s of effective software project management are: People, Product, Process and Project.
Detailed explanation-2: -Explanation: Effective software project management focuses on the four P’s: people, product, process, and project.
Detailed explanation-3: -There are 4 critical components puff project management which is known as the ‘4Ps” namely Product, Process, People, Project.
There is 1 question to complete.