Which of the following is the BEST approach for estimation?
A
Expert opinion
B
Analogy
C
Disaggregation
D
A combination of all of the above
Explanation: 

Detailed explanation-1: -The bottom-up approach is more effective in agile estimation. A person who will complete the task can better tell how much time and effort it would take to complete a work item. Hence, they can offer more practical and reliable project estimates.

Detailed explanation-2: -Which of the following is the best approach for running an effective workshop? Explanation : The best approach for running an effective workshop is Facilitation.

Detailed explanation-3: -Agile estimation helps for proper planning, management and estimation of the total efforts that will be used for implementing, testing and delivering the desired product to the customers in terms of time within the specified deadlines. A well-prepared preliminary estimate is essential.