Which of these is not one of the phase names defined by the Unified Process model for software development?
A
Inception phase
B
Elaboration phase
C
Construction phase
D
Validation phase
Explanation: 

Detailed explanation-1: -Inception: defines the scope of the project and develop business case. Elaboration: Plan project, specify features, and baseline the architecture. Construction: Build the product. Transition: Transition the product to its users.

Detailed explanation-2: -Within the Unified Process, each cycle contains four phases.

Detailed explanation-3: -The linear sequential model, prototype model and spiral model are examples of a software process model. Each model has a different approach to the flow of processes for developing a software. The COCOMO model, on the other hand, is a cost estimation model.

Detailed explanation-4: -The typical software development process consists of several phases: requirements-gathering, high-level design, low-level design, coding and unit testing, integration testing, and deployment.