Which one of the following is performed during the requirements analysis activity?
|
Identify requirements
|
|
Build a prototype
|
|
Identify any ambiguity, inconsistency, and incompleteness in the gathered requirements
|
|
Analyze and allocate resources for requirements specification
|
Explanation:
Detailed explanation-1: -Explanation: Economic feasibility (cost/benefit analysis), Technical feasibility (hardware/software/people, etc.) and Legal feasibility studies are done in Requirement Analysis.
Detailed explanation-2: -Successful completion of the Requirements Analysis Phase should comprise: Definition of approved requirements. Creation of the Functional Requirements Document and Requirements Traceability Matrix. Development of planned test activities.