Which phase of waterfall model takes more time?
A
Requirement gathering
B
Construction
C
Design
D
Deployment
Explanation: 

Detailed explanation-1: -The testing phase consumes the maximum effort in waterfall model.

Detailed explanation-2: -Description: The sequential phases described in the Waterfall model are: 1. Requirement Gathering-All possible requirements are captured in product requirement documents.

Detailed explanation-3: -Requirement Gathering and analysis − All possible requirements of the system to be developed are captured in this phase and documented in a requirement specification document. System Design − The requirement specifications from first phase are studied in this phase and the system design is prepared.

Detailed explanation-4: -Disadvantages of the Waterfall methodology. Changes that come further in the process can be time-consuming, painful, and costly. Other reasons the Waterfall methodology may not work include: Projects can take longer to deliver with this chronological approach than with an iterative one, such as the Agile method.