MCQ IN COMPUTER SCIENCE & ENGINEERING

COMPUTER SCIENCE AND ENGINEERING

SOFTWARE ENGINEERING

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
You are working in XYZ as a project manager. Company wants to develop a project. You are also involved in planning team. What will be your first step in project planning?
A
Establish the objectives and scope of the product.
B
Determine the project constraints
C
Select the team.
D
None of the above.
Explanation: 

Detailed explanation-1: -The first step toward defining project scope is to create a statement of work . This is the official document that outlines the requirements for a particular project. It includes a general description of the work requested, a timeline, a schedule, any special skills necessary and the work location.

There is 1 question to complete.