How many hydro-electric projects in Arunachal Pradesh to be commissioned in 2018?
|
2
|
|
5
|
|
4
|
|
6
|
Explanation:
Detailed explanation-1: -Commissioning of the 600 MW Kameng Hydro Electric Project and the 110 MW Pare Hydro Electric Project was delayed by about a couple of months due to floods and landslides.
Detailed explanation-2: -3.1 As stated, Arunachal Pradesh has a hydropower potential of over 57000 MW.
Detailed explanation-3: -NEEPCO commissioned its largest Hydro Project Kameng(600 MW) in the N.E. Region, Commercial operation of Unit-I (150MW) was declared w.e.f. 00:00 hours of 17.06.