Detailed explanation-1: -The jetty will connect Kaninali in Bhadrak district and Talachua in Kendrapara in Odisha. The project will reduce road distance of around 200 km from Talachua to Dhamra .
Detailed explanation-2: -The Government of India recently approved Rs 50 crores to develop an all-weather ROPAX in Odisha. The total cost of the project is estimated to be Rs 110 crores. The project aims to launch Roll-on or Roll-off Passenger Jetty connecting Kaninali in Bhadrak district and Talachua in Kendrapara district. About the project.
Detailed explanation-3: -Dhamara is a joint stream in Odisha that is formed by the confluence of the Brahmani and Baitarani rivers south of the town of Chandabali. It lies in the Bhadrak district and empties into the Bay of Bengal.