The fifth Scorpene-class submarine, Vagir is scheduled to be commissioned into service in which month?
A
March
B
February
C
January
D
April
Explanation: 

Detailed explanation-1: -Indian Navy’s fifth stealth Scorpene class Submarine INS Vagir was commissioned into the Indian Navy today, 23 Jan 2023 at the Naval Dockyard Mumbai in the presence of Adm R Hari Kumar, Chief of the Naval Staff, the Chief Guest for the ceremony. INS Vagir is named after a “Sand Shark”.

Detailed explanation-2: -Indian Navy is set to commission the fifth Kalvari class submarine Vagir on 23 Jan 2023, Adm R Hari Kumar, Chief of the Naval Staff will be the Chief Guest for the ceremony. These submarines are being built in India by the Mazagon Dock Shipbuilders Limited (MDL) Mumbai, under collaboration with M/s Naval Group, France.

Detailed explanation-3: -The fifth Scorpene class conventional submarine was commissioned into the Indian Navy as INS Vagir in the presence of Chief of Naval Staff Admiral R. Hari Kumar at Naval Dockyard Mumbai on Monday.

Detailed explanation-4: -INS Kalvari, the first Scorpene-class submarine built for the Indian Navy, will be fitted with an indigenous Air Independent Propulsion (AIP) system developed by the Defence Research and Development Organisation (DRDO), the Ministry of Defence (MoD) has said in a statement.

Detailed explanation-5: -The fifth submarine of the Project – 75, Kalvari Class submarines, Yard 11879 was delivered to the Indian Navy today, 20 Dec 22.