SOFTWARE ENGINEERING

SOFTWARE PROJECT MANAGEMENT

RISK MANAGEMENT

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Question 26 of 100Question ID:613609An unusually harsh winter has caused a project to fall behind schedule, and action must be taken to get the schedule back on track. The agreed-upon risk response for this situation is to compress the schedule by approving overtime pay. The project manager recalls a similar situation from a previous project and wants to understand the effectiveness of that particular response plan.What should the project manager do to obtain this information?
A
ACheck the lessons learned register
B
BConsult the risk management plan
C
CGather information from the team members who worked on the previous project
D
DResearch the lessons learned repository
Explanation: 
There is 1 question to complete.