Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
What form of documentation/diagram is the most appropriate for showing the schedule and timelines for activity in a project?
A
Gantt chart
B
Storyboard
C
Data flow diagram
D
System flowchart
Explanation: 

Detailed explanation-1: -One aspect of project planning is organizing project activities, deliverables and timelines.

Detailed explanation-2: -Gantt charts are useful for planning and scheduling projects. They help you assess how long a project should take, determine the resources needed, and plan the order in which you’ll complete tasks.

Detailed explanation-3: -Gantt charts, or Gantt diagrams, are project management tools used to analyze and plan projects. Gantt charts plot the estimated duration of tasks against a timeline, providing a graphical representation of the project’s progress over time.

Detailed explanation-4: -A Gantt chart is a project management tool that illustrates work completed over a period of time in relation to the time planned for the work. It typically includes two sections: the left side outlines a list of tasks, while the right side has a timeline with schedule bars that visualize work.

Detailed explanation-5: -Gantt charts can help you visualize what you need to do and how long each task will take, as well as provide a visual of the overall timeline and deadlines. Gantt charts are most effective when you use them as a visual representation of all tasks that you need to complete in order for the overall project to succeed.