Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
which of the following is not a factor in the failure of the systems development projects?
A
Size of the company
B
Inadequate user involvement
C
Failure of system integration
D
Continuation of a project that should have been cancelled
Explanation: 

Detailed explanation-1: -A failure to plan, lead, manage and monitor the project is a core factor that results in their implementation failure, because the ERP system is complex, and project teams are required to collaborate with top management, different departments, users and consultants during implementation process.