Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Conversion strategies used to change from old system to new system.
A
True
B
False
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -Direct Conversion 2. Parallel conversion 3. Modular Conversion 4. Phase-In Conversion.

Detailed explanation-2: -What are the four conversion strategies and under what circumstances are each strategy the best approach? The four conversion strategies are as follows: direct changeover, parallel operations, phased implementation, and pilot implementation.

Detailed explanation-3: -Conversion is the process of changing from the old system to the new system. Four main conversion strategies can be employed: the parallel strategy, the direct cutover strategy, the pilot study strategy, and the phased approach strategy.