Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Identify which statement related to the activities-Convert to the new system
A
Direct conversion
B
Parallel conversion
C
Pilot conversion
D
Phased conversion
Explanation: 

Detailed explanation-1: -Gradual, or phased, conversion attempts to combine the best features of the two previously mentioned plans, without incurring all the risks. In this plan, the volume of transactions handled by the new system is gradually increased as the system is phased in.

Detailed explanation-2: -Phased implementation is a method of System Changeover from an existing system to a new one that takes place in stages.

Detailed explanation-3: -In the phased approach conversion strategy, the new system: replaces the old one at an appointed time. is introduced to a limited area until it is proven to work properly.