Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Install and test new system is done in which phase?
A
Planning
B
Analysis
C
Design
D
Implementation
Explanation: 

Detailed explanation-1: -Implementation Phase System performance is compared to performance objectives established during the planning phase. Implementation includes user notification, user training, installation of hardware, installation of software onto production computers, and integration of the system into daily work processes.

Detailed explanation-2: -Stage 5: Testing In this fifth phase of SDLC, the testing is done to ensure that the entire application works according to the customer requirements. After testing, the QA and testing team might find some bugs or defects and communicate the same with the developers.

Detailed explanation-3: -Conducting stage-appropriate implementation activities is necessary for successfully utilizing new practices and for organizations and systems to change to support new ways of work. There are four functional Implementation Stages: Exploration, Installation, Initial Implementation, Full Implementation.

Detailed explanation-4: -The testing phase of the software development lifecycle (SDLC) is where you focus on investigation and discovery. During the testing phase, developers find out whether their code and programming work according to customer requirements.

There is 1 question to complete.