Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Reviewing project request is done in which phase?
A
Planning
B
Analysis
C
Design
D
Implementation
Explanation: 

Detailed explanation-1: -At the end of the initiation phase, a phase review is performed. This is a checkpoint to ensure that the project has achieved its stated objectives as planned. A phase review form is completed to formally request approval to proceed to the next phase of a project.

Detailed explanation-2: -The purpose of the Analysis Phase is to thoroughly examine and evaluate the viable options identified in the Feasibility Phase and to arrive at an optimum high-level solution that will satisfy the client’s requirements and the project’s constraints.

Detailed explanation-3: -In the design phase, one or more designs are developed, with which the project result can apparently be achieved. Depending on the subject of the project, the products of the design phase can include dioramas, sketches, flow charts, site trees, HTML screen designs, prototypes, photo impressions and UML schemas.

Detailed explanation-4: -PHASE 4: REQUIREMENTS ANALYSIS PHASE Documentation related to user requirements from the Concept Development Phase and the Planning Phase shall be used as the basis for further user needs analysis and the development of detailed requirements.

Detailed explanation-5: -Answer. Performing a detailed analysis of the old system is taken care of in the Analysis Phase.