FUNDAMENTALS OF COMPUTER

SYSTEMS DEVELOPMENT ANALYSIS

SYSTEMS DEVELOPMENT LIFE CYCLES

Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
The iterative SDM allows for the stages of the SDLC to be completed in any order.
A
True
B
False
C
Either A or B
D
None of the above
Explanation: 

Detailed explanation-1: -The new seven phases of SDLC include planning, analysis, design, development, testing, implementation, and maintenance.

Detailed explanation-2: -The first step of SDLC is Preliminary Investigation and Analysis.

Detailed explanation-3: -There are usually six stages in this cycle: requirement analysis, design, development and testing, implementation, documentation, and evaluation.