Question [CLICK ON ANY CHOICE TO KNOW THE RIGHT ANSWER]
Which feasibility test present below?"Measures whether the organization has or can obtain the hardware, software, and people needed to deliver and support the proposed information system.”
A
Technical Feasibility
B
Economic Feasibility
C
Schedule feasibility
D
Operational feasibility
Explanation: 

Detailed explanation-1: -This assessment focuses on the technical resources available to the organization. It helps organizations determine whether the technical resources meet capacity and whether the technical team is capable of converting the ideas into working systems.

Detailed explanation-2: -Technical feasibility assesses the current resources (such as hardware and software) and technology, which are required to accomplish user requirements in the software within the allocated time and budget.

Detailed explanation-3: -Technical feasibility is a standard practice for companies to conduct feasibility studies before commencing work on a project. Businesses undertake a technical feasibility study to assess the practicality and viability of a product or service before launching it.

Detailed explanation-4: -Operational Feasibility It analyzes whether the users will be affected and they accept the modified or new business methods that affect the possible system benefits.

Detailed explanation-5: -Technical feasibility-The technical feasibility study basically centers on alternatives for hardware, software and design approach to determine the functional aspects of a system.